This project, encompassing construction and rehabilitation from Byron to San Jose, was the continuation of the original South Bay Aqueduct/Pipeline rehabilitation project.

To complete this project Syblon Reid:

  • Constructed the addition of over 30 manholes
  • Added continuity bonds to over 15 miles of pipeline
  • Recoated the interior of existing, 54-inch, 60-inch, and 72-inch pipeline
  • Performed tank piping and structural modifications
  • Performed soil nailing and slope stability improvements
  • Replaced over 50 Automatic Relief Valves (ARV) and blow-off piping systems
  • Performed extensive Asbestos remediation
 

Syblon Reid completed these critical outages ahead of schedule, which
included additional scope of work

 

 