|
at Little Dry Creek
| The Western Canal Water District (WCWD) was
faced with a significant safety hazard and regional water flow
inconsistencies. Prior to the construction of the realigned
canal, siphon, and meter test station, manually operated slide
gates controlled the water flow adjacent to Nelson Road. When
flooding occurred across Nelson Road the WCWD district operators
would open the flood gates by hand. This created a great safety
hazard for the district operators and the Nelson community.
This intermittent flooding would also disrupt the integrity
of neighboring farmers' water flow and the water fowl habitat
ecosystem. |
|
 |
To correct the Little Dry Creek water issues, WCWD
chose Syblon Reid's carefully selected design-build team of geotechnical,
structural, environmental engineering firms, and custom engineering
contractor crafts to perform this design-build project.
WCWD
credits Syblon Reid with saving their district at least six months
construction time on this project.
Technical aspects of this project included:
25,000 cubic yards of excavation
Construction of a 200 foot concrete siphon
Construction of a Replogle Flume meter test station
Demolition of the existing manually operated sluice
gates
Realignment of the Little Dry Creek canal
|